The Power Elite:
The Politics and Ecology of Malaysia's Bakun
Dam
Stephen Bocking
Assistant Professor, Environmental History
Trent University
Associate Editor, Alternatives
Note: This article previously appeared in Alternatives Journal
23:2 (Spring 1997) pp.14-19
Summary:
There was much relief in June 1990 when Prime Minister
Datuk Seri Mahathir Mohamad of Malaysia announced cancellation of the Bakun
Dam project, proposed for the interior of the state of Sarawak. No wonder:
it would have flooded more than 69,000 hectares of tropical forest, and
displaced more than 5000 people, to generate at great cost electricity
for which there was no immediate market.
Nearly seven years later, workers and machinery are busy constructing access
roads, camps, and diversion tunnels at the dam site, and clearing forest
from the reservoir area. The Bakun Dam is underway. Government and business
elites, led by the prime minister, have staked their prestige on the project,
even as protests mount, and doubts grow about its economic, environmental,
and technical viability.
Why was the Bakun Dam revived? The scale alone of the project makes the
question important. Large dams usually have large social and environmental
impacts, and this--the largest in South East Asia--will, if completed,
be no exception. But the story of the Bakun Dam can tell us about more
than just dams. Even as cost and environmental concerns force an end to
the era of large dams in Canada, this technology is still being promoted
elsewhere, particularly in Asia and South America. An examination of the
recent history of the controversy concerning the Bakun Dam can help demonstrate
how decisions about development, in Malaysia, as in much of the developing
world, are made by a few, for the benefit of a few.
Origins and First Demise of the Project
The hydro potential of Sarawak--a predominantly forested, relatively lightly
populated Malaysian state on the island of Borneo--was first examined more
than 30 years ago by Australian surveyors. Subsequent studies identified
numerous potential hydroelectric sites, including Bakun, while another
study found that while thermal power plants would be slightly cheaper to
build, a dam at the Bakun site would have lower operating costs. By 1986,
accordingly, the Malaysian government had decided to proceed.(1)
The Bakun Dam, 204 meters in height, would be the largest dam in South
East Asia.
The dam's potential consequences immediately raised concern. Besides flooded
forests and displaced inhabitants, worries included the possibility of
dam collapse, earth tremors, new waterborne diseases, and sediment accumulation
behind the dam that would render it useless within fifty years. There were
also questions about cost: the necessary loans would likely substantially
increase Malaysia's foreign debt. It was even unclear whether the nation,
then in recession, needed so much electricity.(2)
These problems were far from unprecedented. By this time, as Edward Goldsmith
and Nicholas Hildyard had argued in their 1984 review, The Environmental
and Social Impacts of Large Dams, such problems had become commonplace
with this technology. The "benign superdam": a clean source of energy,
generating benefits at reasonable cost, was, they concluded, a myth.(3)
Protests by indigenous peoples affected by the project, and by other concerned
Malaysians, as well as doubts about economic viability, led Mahathir to
shelve the Bakun Project. He announced the decision at the June 1990 international
conference on conservation of tropical biodiversity. Mahathir claimed that
it demonstrated Malaysia's commitment to conservation.(4)
Reviving the Project
Three years later, on September 9, 1993, the Malaysian cabinet reversed
this decision, again approving construction of the Bakun Dam, to generate
2400 MW, at a cost of approximately $7 billion Canadian.(5)
Now, it was argued, Malaysia's need for power justified the project. By
1993 the Malaysian economy was growing by more than 8 percent per year,
with electricity demand expanding even faster. Blackouts in 1992 and 1993,
and a predicted doubling of demand by 2000, were harbingers of a power
crisis, justifying extraordinary efforts to expand supply.(6)
Project proponents also believed the Bakun Dam could help reduce dependence
on fossil fuels, especially oil. Most evident, however was that this project
was consistent with an energy policy relying almost entirely on supply.
As environmentalist Gurmit Singh noted in December 1995, "The concept of
energy conservation and certainly its implementation is virtually absent
in Malaysia."(7)
But in a way, the scale of the project was its own justification. The Malaysian
government has defined a national "vision" of full industrialization by
2020, and sees megaprojects as central to its achievement. A new international
airport, highways, the world's tallest office towers in Kuala Lumpur, a
new capital city--all reflect a preference for grandiose projects. The
Bakun Dam--the tallest, most powerful, most expensive dam in South East
Asia--indeed fits well within this view of development.
In the following months, however, it became apparent that more was at stake
than just electricity. On January 30, 1994 Mahathir announced that the
contract for constructing and operating the dam had been awarded, without
tender, to Ting Pek Khiing, a Sarawak timber tycoon and developer, and
his company, Ekran Berhad. This surprised many, because Ting had no previous
experience building dams. What he did have, however, was the prime minister's
confidence. Mahathir's announcement was only the public culmination of
intense private lobbying, through which Ting had convinced him that his
company could deliver the project quickly. Ting had also won the support
of the Sarawak Chief Minister, because his proposal would further the minister's
goal of the privatization of utilities, while directing business to Sarawak
companies. Thus, Ting's success reflected as much his responsiveness to
the political priorities of senior officials, as his ability to address
Malaysia's energy needs.
In the three years since Ting won the contract, complex networks of influence
have been woven around the project, linking politicians, business leaders,
and members of their families. Much of the details of these networks remain
secret: as one account concludes, "It is a story of which the full details
may never be known, involving as it does maneuverings, meetings, lobbying,
rapid changes of minds and deployments -- a real intrigue, mostly behind
closed doors and to which the public has had little access."(8)
The project's revival immediately drew attention from dam builders around
the world, including Canadians. In February 1994 representatives of BC
Hydro, Hydro Quebec, Ontario Hydro, and several Canadian engineering firms
together visited Malaysia, to promote their participation in the project.
During the January 1996 trade mission to Malaysia, Prime Minister Jean
Chretien met with Mahathir, and reiterated Canada's interest in the project,
while Ontario Hydro International opened an office in Sarawak, reinforcing
a relationship it had been developing for several years with Malaysian
power suppliers, partly through the support of the Canadian International
Development Agency.(9)
Generating New Concerns
As it had in the 1980s, the project has elicited a variety of concerns,
and has led to formation of a popular movement, the "Coalition of Concerned
NGOs Against the Bakun Dam". Since late 1993 their concerns have coalesced
around resettlement, environmental impact issues, and economic and technical
problems.
Resettlement:
The project would compel relocation of more than 9,000 people, who would
lose their land, homes, and every other aspect of 18 communities. Most
are now subsistence farmers, with some supplementing their income through
cash crops or jobs in timber companies. They value their autonomy: as one
stated: "We are poor only insofar as we have little money. In fact, we
are rich, because we have all we need to feed ourselves and house ourselves.
Rice is free, fish and meat are free, vegetables are free, water is free,
lumber is free".(10) After relocation
they would likely no longer have their own land, but might have to seek
work instead on large plantations.
A few hundred kilometers from the Bakun site sits the smaller Batang Ai
dam, completed in 1985. For that project, 3000 people were relocated to
an area lacking adequate farmland or jobs, even before their new homes
were ready. Many have not yet received fair compensation, and almost half
have returned to near their original homeland. Relocation plans at the
Bakun site appear not to have benefited from this experience: the time
frame for completing the resettlement (by 1998) is unrealistically short,
and plans make little provision for the preferences of those to be relocated.
While many would prefer to move to higher ground within the catchment area,
plans call instead for a move to an area with poorer land and fewer prospects.(11)
This reflects a general failure to consult with those affected. As Nyaban
Kulleh, a resident of one of the communities to be flooded told a journalist
in 1994: "no one has come forward to tell us what is happening. We don't
want to go against the Government. But if the Government wants the Bakun
project, why don't they think of us? They say this is development but we
don't think that flooding our homes is development."(12)
These problems of resettlement also reflect Sarawak's place within the
national economy, and the relations between Sarawak citizens and their
own government. Historically, Sarawak has served as a resource hinterland,
exporting timber, oil, and gas, while other sectors of its economy have
remained relatively underdeveloped. The Sarawak government has helped perpetuate
this status, encouraging rapid exploitation of resources, while obstructing
efforts by indigenous peoples to assert control over, or benefit from,
this exploitation.(13)
Environmental Impacts:
When the project was announced in September 1993, the government stated
that it "will give special consideration to the project to ensure it does
not harm the natural environment and ecology."(14)
Construction would not begin until after public review of an environmental
impact assessment (EIA) report, as required by Malaysia's Environmental
Quality Act (1974).
Soon, however, the EIA process started to unravel. In early 1994 Ekran
assigned preparation of the EIA report to the Kuching campus of the University
of Malaysia. Progress in the study was slow; by September 1994 field work
had not yet even begun. In February 1995 the EIA process was broken into
four parts, so that each component of the project could be approved separately.
The objective was speed: if the reservoir EIA was approved first, forest
clearing could begin before approval of the dam, transmission lines, or
undersea cable. This maneuver, described by opponents as "nonsensical",
aroused concern even among supporters, with a pro-government newspaper
describing it as equivalent to approving a house one floor at a time.(15)
Reinforcing the perception that the EIA process had become only a formality,
Ting stated on submitting the EIAs in February 1995 that clearing of the
reservoir area would soon begin, because "we are confident that all the
EIAs will be approved. There is no reason for rejection because we have
a team of experts and consultants to ensure measures taken in the project
are in compliance with the DOE's [Department of Environment's] requirements."
(16) Government officials echoed
his confidence. And six weeks later, on March 27, 1995, the first EIA was
approved, without ever being released to the public.
But it was not even immediately clear who had approved it. Only on April
6 was it clarified that, retroactive to September 1994, jurisdiction over
the EIA had been transferred from the federal to the Sarawak government.(17)
Unlike the federal government, the Sarawak government did not require public
review of the EIA report prior to approval. Soon after, parts two and three
of the EIA were also approved, again without public review.
Finally, in May 1995 the public was permitted to view the EIA report, including
its optimistic conclusion, that the "proposed Bakun Hydroelectric Project
will supply the nation with cheap, clean, and reliable electricity". The
dam would also provide a range of other benefits, including improved conditions
for those affected, flood control, and better river navigation. Environmental
problems, it concluded, could be minimized. For example, sedimentation
could be reduced to an "acceptable level" that would not affect the project.
Other impacts were less than feared, because of damage that had already
occurred. For example, since the reservoir area had already been disturbed
by shifting cultivation, impacts would be less severe than if the area
were virgin forest. Remarkably, the EIA even claimed that the dam would
reduce loss of forests, even though site preparation for the reservoir
involved clearing the entire area.(18)
Shortly after its release, the EIA report was evaluated by the International
Rivers Network (IRN). The Network identified numerous shortcomings. While
the EIA had identified a range of impacts, including deterioration of reservoir
and downstream water quality, impacts on downstream water levels and salt
water intrusion, risk of waterborne diseases, loss of fish habitat, and
inundation of terrestrial habitat, most of these impacts were not reflected
in the EIA's optimistic conclusions.
The evaluation also concluded that the EIA's "usefulness is severely limited
by basic methodological flaws". It had failed to explain why the dam was
needed, or to consider adequately the no-project alternative, or other
sources of energy. Nor did it evaluate long-term impacts, or interactions
between different impacts, such as the effect of water quality on fisheries.
It did not even estimate adequately the life-span of the project. Numerous
key issues were not addressed at all, and the report relied too much on
inadequate data or uncertain predictions. In sum, the IRN said, the EIA
"would not meet internationally accepted standards for environmental assessments",
and gave no evidence of having benefited from past experience with large
reservoirs in tropical areas.(19)
Economic and Technical Problems:
Since 1993 Malaysia's generating capacity has expanded greatly, with new
plants being constructed by the national utility and by independent producers.
The margin of supply over demand has increased to about 50 percent, with
several additional plants expected to be completed within the next few
years.(20) As a result, the need
for power from Bakun has become much less evident.
Even if its power will be required when the dam is ready in 2002, it will
be more expensive than that available from other sources. Ekran has signed
a contract to sell electricity to the national utility at a rate higher
than that offered to independent power producers, and about double the
cost of power from the utility's own stations. Even at this rate, much
doubt has been expressed that the project will be economically viable.
(21) Ultimately, according to many
critics, the cost of the project will be borne by the national electric
utility, and by the Malaysian public, through higher electricity rates,
direct subsidies, or both.
There are also many uncertainties concerning technical details. One of
the most significant relates to the cables that will deliver power to the
Malaysian mainland. They are, in effect, an unprecedented experiment. At
650 km, they are far longer than the longest existing undersea power cables,
between Denmark and Sweden. No reliable estimates of how much these cables
will cost, how long they will last, or how much power will be lost as it
travels through the cable, are yet available.
Secrecy and Determination
These concerns led to the inevitable question: why build a dam that will
have serious environmental and social impacts, and that requires an untested
undersea cable, to supply industrial centres now enjoying an overabundance
of less expensive electricity? This question has been the focus of much
debate within Malaysia. This debate, however, has been muffled by persistent
secrecy.
In the absence of genuinely open access to information, media coverage
of the controversy tends to focus on the government view, with mention
of opponents' views limited to indirect references. Various rhetorical
devices also discourage dissent. For example, those affected have been
urged to be willing to make sacrifices for the good of Malaysia. The implicit
message is that to protest is to be selfish and unpatriotic.
Opponents are also described as being influenced by foreigners. In February
1995, for example, one government minister said of Friends of the Earth
Malaysia (SAM) that "If they follow the dictates of the western environmental
NGOs, then we have to stop living and not develop anything at all." Retorted
the president of SAM, "after 38 years of independence, our politicians
should have the political maturity to engage in a healthy debate when confronted
with controversial issues." (22)
Restrictions on information have also permitted proponents to present their
own interpretation of events. For example, before release of the EIA reports
Ting was able to present them as concluding that the project would have
"no adverse impact to the surroundings". The government even asserted,
without effective challenge in the mainstream media, that the dam would
have environmental benefits, including less air pollution, flood control,
reduced soil erosion, parks and wildlife sanctuaries. (23)
Similarly, it has been difficult even to discuss who will benefit from
the project. While there is evidence that beneficiaries will be limited
to Ting and other members of the Malaysian business community, as well
as foreign companies selling technology or expertise, their interests have
tended in public debate to be conflated with the national interest, through
repeated assertions by government and business that the project will serve
national economic needs.
The government has repeatedly demonstrated its determination to continue
the project, particularly during the summer of 1996. On June 19th, high
court judge James Foong, ruling in favour of three Sarawak individuals
affected by the project (who had argued that they had not been adequately
consulted, as required by the Environmental Quality Act), declared that
the transfer of authority over the EIA from the federal to the state government
was invalid. The project therefore could not continue until it met federal
requirements, including public review of the EIA. Public review, Foong
stated, was essential, since "the interaction between people and their
environment is fundamental to the concept of impact." Further, he argued,
"It makes a mockery of the whole issue to say that the EIA can be approved
first and if the public has any constructive ideas, they can submit later.
This certainly is illogical, deprivation of good sense and sound reasoning."(24)
Foong's decision was hailed by environmental groups, but was viewed by
the government as, at most, an inconvenience. The federal and state governments
filed four appeals, and on July 12, Ekran obtained a Court of Appeal order
allowing work to proceed. Since then, momentum for the project has continued
to build. During the September 1996 Sarawak elections, the major parties
successfully resisted pressure to make the dam a campaign issue. Manipulation
of public perceptions also continues. In Kuching, Sarawak's capital, the
most visible signs of the project are billboards extolling its contribution
to the state's economic progress.
But doubts also continue to mount. In July 1996 Delphi International, a
British consulting firm, warned its clients that the Bakun Dam promised
far greater risks than is typical of power projects, and lower returns.
(25) This has presented an additional
obstacle to Ekran's efforts to attract foreign investment. Postponement
in September 1996 of the signing of a major contract between Ekran and
the engineering firm Asea Brown Boveri (ABB) has also hinted at the impact
of the international campaign against the project. Thus, more than three
years after announcement of the project's revival, the final outcome remains
uncertain.
Debating Development
Obviously, the merits of a project as important as the Bakun Dam should
be publicly debated, so that those affected, whether directly, or indirectly,
can contribute to an informed decision. In Malaysia, this debate has been
hindered by restricted access to information, and limitations on media
coverage of opposing points of view. While Canada and other nations have,
increasingly, rejected large dams (as reflected in recent experience in
British Columbia and Quebec), this technology is still being promoted in
countries like Malaysia, in part because the political environment hinders
the open debate that has led to its rejection elsewhere. In the absence
of open accountability, proponents within both government and the private
sector are able to seek large profits from the project, while discounting
those costs--economic, environmental, and social--that will be borne by
Malaysian society.
The Bakun project especially demands debate because there is more at stake
than simply one dam. Such projects present a stark conflict between two
conceptions of development: that implied by a technology imported from
the industrialized world, intended to supply distant centres through a
national energy system; and that implied by the communities it threatens
to displace, whose economies remain based on local resources, regional
trading relationships, and indigenous cultures. Such conflicts and debates
concerning development are often not immediately apparent to many Canadians,
who tend to see only export opportunities in the rapidly growing economies
of the Asian Pacific rim.
Malaysia, like many other nations, has developed a body of environmental
law that requires open examination of large projects. Events of the last
few years, however, indicate that such requirements are not sufficient.
Clear delineation of federal and state responsibilities is also necessary,
as are specific requirements concerning the environmental impact process,
including the timing of studies, public review, and decisions concerning
approval.(26) The Bakun experience
demonstrates once again that EIAs done in haste, and toward the end of
the planning process, are most likely to be formalities, and will fail
to integrate environmental concerns in the development process.
But effective EIA requirements also depend on political will, enforced
by open debate about projects, and about the development process itself.
Recent discussions of the social role and character of debate and dissent
has focused on the concept of the "civil society" -- a political context
within which individuals, groups, civic organizations of all types are
able to express themselves, debate their concerns, and, generally, mediate
the relationship between the state and the citizen.(27)
The recent history of the Bakun project demonstrates how obstacles to a
civil society can be formed by restricting access to information, and by
discouraging the questioning of official priorities. But it also demonstrates,
paradoxically, how such a project can contribute to a civil society. In
Malaysia, as elsewhere, developments eliciting immense environmental, social,
and economic concerns have often led to stronger organizations of concerned
citizens, because such developments demonstrate so effectively the need
for civic oversight of the exercise of state and private authority.
Endnotes
-
"Harnessing Bakun," New Straits Times (May 17, 1994)
Back to Text
-
"Bakun: Between Energy & Tragedy," Utusan Konsumer
(February 1986) p.9.
Back to Text
-
Edward Goldsmith & Nicholas Hildyard, The Social
and Environmental Effects of Large Dams (San Francisco: Sierra Club
Books, 1984) and Philip B. Williams, "Learning from the Mistakes of Large-Scale
Water Development," Water Nepal 1994, 4(1): 36-39.
Back to Text
-
"Full details of Bakun hydro-electric project needed,"
(Penang: Friends of the Earth Malaysia, Press release, 22 September 1993).
Back to Text
-
"Go-ahead for RM30.6bil Bakun project," New Straits
Times (September 10, 1993) and "2,400MW from Bakun Project Likely by
2005," Business Times, (October 1, 1993).
Back to Text
-
"The Power Sector in Malaysia--Towards Meeting the National
Requirements," (Kuala Lumpur: Malaysia Ministry of Finance, Economic Report
1994/95), p.94.
Back to Text
-
Insan, Power Play: Why the Bakun Hydroelectric Project
is Damned (Kuala Lumpur: Insan, 1996) p.46. Gurmit Singh is a former
president of the Environmental Protection Society of Malaysia.
Back to Text
-
ibid. p.7. Close links between resource extraction
and government officials are common in Sarawak. For example, the Sarawak
environment minister also holds major timber concessions.
Back to Text
-
"Canada Keen on Projects in Malaysia," The Star
(Kuala Lumpur: January 19, 1996); "Ontario Hydro to open representative
office in Kuching," The Borneo Post (January 21, 1996). In recent
contracts announcements, Canadian firms have been conspicuously absent,
with firms from Europe, Latin America and Asia receiving major contracts
for the project.
Back To Text
-
Jerome Rousseau, "The Bakun Hydro-electric Project and
resettlement: a failure of planning," (Conference on the Bakun Hydro-electric
Project Kuala Lumpur, December 2-3, 1995), p.8.
Back to Text
-
ibid.Rousseau, an anthropologist, has studied the
socio-economic aspects of the Bakun Project, as a consultant for the Sarawak
State Planning Unit.
Back to Text
-
"Compensation a thorny issue," New Straits Times,
(May 18, 1994).
Back to Text
-
Wee Chong Hui, Sabah and Sarawak in the Malaysian Economy,
(Kuala Lumpur: S. Abdul Majeed & Co., 1995); and Colin Nicholas, Raajen
Singh, (eds.), Indigenous Peoples of Asia: Many Peoples, One Struggle,
(Bangkok: Asia Indigenous Peoples Pact, 1996).
Back to Text
-
"Go-ahead" NST, (September 10, 1993). See Note
5
Back to Text
-
As excerpted in Aliran Monthly Vol. 16(5), 1996.
See Note 7.
Back to Text
-
"Bakun dam: Forest-clearing to begin in April," New
Straits Times (February 18, 1995).
Back to Text
-
"EIA for Bakun Dam Subject o Sarawak Regulations" New
Straights Times (April 7, 1995).
Back to Text
-
Ekran Berhad, "Privatisation of the Bakun Hydroelectric
Project; Detailed Environmental Impact Assessment for Reservoir Preparation,"
(Kuala Lumpur: February 1995) reproduced for Conference on the Bakun
Hydro-Electric Project (December 2-3 1995)
Back to Text
-
Philip B. Williams et al., "A Review of the Environmental
Impact Assessment [Interim Report] of the Bakun Hydroelectric Project Prepared
for Ekran Berhad," (Berkley, California: Prepared for the International
Rivers Network, June 1995).
Back to Text
-
Insan, Power Play p.22 (See Note 7
p. 22 and "The Power Sector in Malaysia" (See Note 6 p.
94
Back to Text
-
Insan, Power Play p.41-45
Back to Text
-
"Lim takes SAM to task over Bakun dam project," Business
Times (February 20, 1995); and "Sam: Keng Yaik's outburst regrettable,"
The Sun (February 22, 1995).
Back to Text
-
"Harnessing Bakun," (See Note 1.
Back to Text
-
Justice James Foong's Judgment-Some Excerpts" Aliran
Monthly, 16:5 (1996) p. 6.
Back to Text
-
Delphi International, "Bakun: High Dam: High Risk? The
Bakun hydroelectric Project; A Financial Analysis" (London, England: research
report, 8th July 1996).
Back to Text
-
There are evident parallels with the Malaysian situation,
and recent Canadian federal and provincial jurisdictional conflicts, as
seen with the Oldman Dam in Alberta, the Rafferty-Alameda Dam in Saskatchewan,
and the James Bay project in Quebec.
Back to Text
-
See, for example: Eboe Hutchful, "The civil society debate
in Africa," International Journal (1995-96, 51: 54-77); Robert D.
Putnam, "Bowling Alone: America's Declining Social Capital," (i>Journal
of Democracy (1995, 6(1): 65-78).
Back to Text
[Go to Top]
Back to IDSNet Homepage